Turnkey Modular Construction


Client: Principal Technology Engineering
Region: South Louisiana
Location: Placid Refining Company
Services Performed: Procurement, Fabrication and Construction
Contractor: SMI Companies, Inc.
Award: April 2008
Completion: November 2008
Project Manager: Morris Hankins
Key Participants: MMR and I & I
Description:
30 ton sulphur recovery unit, turnkey modular construction built and tested off-site prior to shipment.
Innovations:
This SRU weighing 350 tons at load-out was built in stacked and bolted modular sections. All equipment, piping, steam trace, electrical and controls were installed and functionally tested at our Berwick, LA facility prior to being disassembled and loaded out on a barge. Delivery was made to the Placid Refinery in Baton Rouge, La.

This unit was installed as part of a larger plant expansion in record time with minimal interference to the other projects at the site.
Scope:
  • Lump sum contract
  • Turnkey fabrication
  • Electrical
  • Instrumentation
  • Controls
  • Load out and tie down